There has been plenty of construction activity on site, with works taking place across 205 sites for new homes.
Stages 5, 6 and 8A
Authority approvals are underway on Stage 5. The current inspection times scheduled are longer than originally planned, titles are now anticipated to be received in April.
For Stage 6, construction works are being finalised in preparation for practical completion. Titles are anticipated to be received in May 2023.
Stage 8A is also on track to receive titles in May 2023. For Stage 8A ,titles are dependent on a traffic review by VicRoads and council, which is currently underway. An update will be received in April, which we will share with purchasers.
Stages 7, 8B and 11
For Stages 7 and 11, earthworks are now complete and the installation of sewer, water and drainage is underway. Roadworks have also commenced.
Earthworks are also complete on Stage 8B with drainage currently underway. The installation of sewer will also begin in the coming weeks. Works on these stages are on track for settlements to occur between August and October this year. Visit the Harriott Buyers Portal to check your title date.
Stage 12
Earthworks are anticipated to commence on Stage 12 and Stage 12 Acreage Release in the coming month. This will see another 58 lots ready for new homes in December 2023.
View the latest construction activity with footage captured via drone.
We share regular communications and updates with Harriott purchasers to keep them informed while they wait for their land to settle. To receive these updates please add customerrelations@jinding.com.au and customerrelations@email.jinding.com.au to your safe sender list.