CONSTRUCTION UPDATES

Stages 1 to 3 are currently under construction with the first residents set to begin building their dream homes this year. Visit this page for the latest site news and construction updates.

1
2
3
4
50% Complete

Stage 1

Works are now complete, Practical Completion is anticipated in the coming fortnight.

Stage 1
Construction Update

50%
1
2
3
4
  1. 1Earthworks- Complete
  2. 2Sewer & Drainage - Complete
  3. 3Services - Complete
  4. 4Roads - Complete
  5. 5Landscaping - Complete
  6. 6Authority Approval
  7. 7Titles Lodged
  8. 8Settlement - estimated Q3 2021
Stage 1

Works are now complete on Stage 1. Check back here to see a new image from site every 10 minutes.

 

1
2
3
4
5
6
75% Complete

Stage 2

Authority compliance checks are underway.

Stage 2
Construction Update

75%
1
2
3
4
5
6
  1. 1Earthworks - Complete
  2. 2Sewer & Drainage - Complete
  3. 3Services- Complete
  4. 4Roads - Complete
  5. 5Landscaping- Complete
  6. 6Authority Approval- Underway
  7. 7Titles Lodged
  8. 8Settlement - estimated Q3 2021
Stage 2

Practical Completion has now been achieved on Stage 2. Check back here to see a new image from site every 10 minutes.

1
2
25% Complete

Stage 3

Sewer and Drainage is underway.

Stage 3
Construction Update

25%
1
2
  1. 1Earthworks - Underway
  2. 2Sewer & Drainage
  3. 3Services
  4. 4Roads
  5. 5Landscaping
  6. 6Authority Approval
  7. 7Titles Lodged
  8. 8Settlement - estimated Q1 2022
Stage 3

Works are progressing well on Stage 3. Check back here to see a new image from site every 10 minutes.

Construction Process

1. Earthworks

Construction machinery is brought to the site. Topsoil is stripped and works are undertaken to move the earth and level the land as much as possible. If required, clean fill (dirt) will be added to the site to raise the level of the stage or excess material removed to create an easy level building pad.

2. Sewer & Drainage

Earthworks have now created space for more construction to commence. Excavation of trenches then installation of sewer and drainage pipes are the first of the services to be delivered.

3. Services

Services for your land are installed underground, including water, power (electricity), gas, and telecommunications (internet). Roads may also begin to be formed.

4. Roads

Subgrade works and asphalting of roads, streetlights are installed, footpaths and nature strips are created. It is now we start to see the stage and lots look more like what they did on the plans (called Plan of Subdivision) provided to you.

5. Landscaping

Every good block of land needs its finishing touches! Final street trees are planted, your lot is trimmed, topsoil spread, crossovers installed and pegs (wooden stakes) are installed to help you identify your lot.

6. Authority Approval

Before we lodge your land for a title to be issued, Council undertakes a few checks to ensure the subdivision is delivered in line with the approved design plans.

7. Titles Lodged

Once these checks are complete, titles for the stage are lodged to identify the newly created blocks of land, where you will build your house. Once titles are received, your solicitor/finance broker is notified and will arrange for settlement within 10 working days.

8. Settlement

Once settlement has occurred, the land is ready for your builder to build your dream home on!